New Building Site Picture Selection
Originally there were twenty trees and a building to be removed.
New pictures will be added periodically to show progress.
Please scroll down to the date of pictures you wish to see.
![]()
Please Select the Desired Site Pictures Below:
[ 08 Oct 2004, Tearing down old building]
[ 16 Oct 2004, Removing old building and tree brush]
[ 23 Oct 2004, Removing old building and tree brush ]
[ 23 Oct 2004, Sawing trees and removing brush]
[ 30 OCT 2004, Removing trees and brush ]
[ 30 Oct 2004, Removing tree brush ]
[ 30 Oct 2004, Removing logs and brush ]
[ 04 Nov 2004, Buldozer removing logs & stumps ]
[ 05 Nov 2004, Removing debris and stumps ]
[ 06 Nov 2004, Removing Brush ]
[ 12 Nov 2004, Building site almost cleared ]
[ 26 Dec 2004, Showing construction preparation ]
[ 30 Jan 2005, Showing construction fence around site ]
[ 04 Feb 2005, Digging to tunnel under Mexico Road ]
[ 08 Feb 2005, Prepairing to Drill under street for water main ]
[ 09 Feb 2005, Drilling and inserting pipe under street for water main ]
[ 11 Feb 2005, After the drilling was completed ]
[ 12 Feb 2005, Water main and fire plug installation ]
[ 15 Feb 2005, Digging for sewer pipe installation ]
[ 16 Feb 2005, Fire Plug, Water Main, Some Sewer Drains installed (trees)
]
[ 17 Feb 2005, Cleaning front loader, drilling hole almost filled
]
[ 18 Feb 2005, Building Site Sign, Storm drain system ]
[ 19 Feb 2005, More Building Site Sign, Storm drain system ]
[ 23 Feb 2005, Preparing land for construction of building ]
[ 25 Feb 2005, Truck delivering desicant, large stump, site preparation
]
[ 02 Mar 2005, Preparing foundation trenches and building site ]
[ 02 Mar 2005, Some foundation concrete poured ]
[ 03 Mar 2005, More foundation concrete poured ]
[ 04 Mar 2005, All foundation concrete completely poured ]
[ 07 Mar 2005, All foundation concrete forms removed, grading performed ]
[ 08 March 2005, Floor area marked for plumbing ]
[ 09 March 2005, Foundation insulation installed, plumbing material delivered ]
[ 10 March 2005, Plumbing work was started ]
[ 11 March 2005, More plumbing work was done ]
[ 16 March 2005, Plumbing inspection done, preparing to pour floor concrete ]
[ 17 March 2005, Ready to pour floor concrete ]
[ 18 March 2005, Pouring and smoothing floor concrete ]
[ 19 March 2005, Pouring and smoothing floor concrete completed ]
[ 23 March 2005, Raising the walls ]
[ 25 March 2005, More raising the walls ]
[ 28 March 2005, Wall framing done, plywood sub siding installed ]
[ 29 March 2005, Some inside wall framing done, outside plywood sub siding finished ]
[ 30 March 2005, More inside wall framing done, ]
[ 31 March 2005, Trusses delivered to site, more inside wall framing done ]
[ 03 April 2005, Inside wall framing appears completed ]
[ 04 April 2005, Building ready for truss installation ]
[ 06 April 2005, Truss installation 1 ]
[ 06 April 2005, Truss installation 2 ]
[ 06 April 2005, Truss installation almost completed ]
[ 07 April 2005, Truss installation complete except for peaks ]
[ 08 April 2005, Truss installation complete with peaks ]
[ 14 April 2005, Church members install sub roofing plywood ]
[ 15 April 2005, Church members finish sub roofing plywood side 1 ]
[ 16 April 2005, Sub roofing plywood done, sub roofing tar paper done side 1, Wiring started ]
[ 18 April 2005, Some Roofing done side 1, some sub roofing tar paper done side 2 ]
[ 24 April 2005, All roofing completed, some electrical, windows, doors installed ]
[ 30 April 2005, More of the following installed: ducts, baptistry,electrical, podium ]
[ 08 May 2005, Ready for brick, more of the following installed: ducts, baptistry,electrical, podium, plumbing ]
[ 09 May 2005, Masonery work started ]
[ 10 May 2005, Brick work progressing ]
[ 14 May 2005, Brick work almost done ]
[ 18 May 2005, Brick work done, side sofits done, most insulation done, electrical wiring trench done
]
[ 19 May 2005, Canopy trusses done, siding 1/2 done ]
[ 23 May 2005, Canopy, siding, wall board, sidewalks almost done ]
[ 30 May 2005, outside of building almost done, inside ready for painting ]
[ 12 June 2005, Progressing Inside ]
[ 22 June 2005, Parking lot progress, progress inside
]
[ 23 June 2005, Parking lot progress, laying asphalt
]
[ 26 June 2005, Parking lot asphalt completed, flowers planted
]
[ 28 June 2005, Parking lot stripes completed, interior progress ]
[ 04 July 2005, Shrubs & flowers planted, airconditioners & doors installed ]
[ 12 July 2005, Ready for carpet installation ]
[ 13 July 2005, Starting to install carpet ]
[ 14 July 2005, Carpet installation, class rooms completed ]
[ 16 July 2005, Carpet installation completed except for cleanup ]
[ 18 July 2005, Pews delivered, installation started ]
[ 19 July 2005, Pew installation completed ]
[ 11 August 2005, Inside Pictures Final 1 ]
[ 11 August 2005, Inside Pictures Final 2 ]
[ 11 August 2005, Inside Pictures Final 3 ]
[ 11 August 2005, Outside Pictures Final 1 ]
[ 10 Sept 2005, Sod lain, grass seed sown in storm drain retaining pond ]
[ 22 Sept 2005, New sign, podium, and communion table
]
[ 07 Oct 2005, New sign with lettering
]